The Dukes in Ashington gets four SEN classrooms, made from buildings moved from Amble and York. Developer contributions pay the £1.25m cost.

The Dukes Secondary School in Ashington is to get four extra classrooms for pupils with special educational needs (SEN).

Northumberland County Council’s Cabinet approved up to £1.25 million for the work on Tuesday 10 November. The council said the scheme will “help meet growing demand for school places” (Northumberland County Council).

Where the classrooms come from

The new rooms are not a new build. The Cabinet report says the scheme will:

  • move a modular building from James Calvert Spence College in Amble, about ten miles north, to The Dukes
  • buy an existing modular building in York, move it to Ashington and refurbish it
  • refurbish the school’s existing caretaker’s building to add classroom space

Together they make four classrooms. Each can take 8 to 10 pupils at a time, depending on their needs.

The report says modular buildings were chosen because they are the “most deliverable short-term solution”. Extensions or a new building would take “significantly longer” to finish.

What it costs, and who pays

Item Cost
Buying, moving and refurbishing the buildings £944,000
Technical adviser £118,000
Contingency £188,000
Total £1,250,000

All of it comes from Section 106 contributions: money housing developers pay the council towards local schools when they build. The report names both secondary and SEN education contributions as the source.

The school will cover the running costs, such as utilities and upkeep. The report says the multi-academy trust that runs The Dukes will take those on under a memorandum of understanding with the council.

Why the council says it is needed

The report is blunt about the alternative. Without the extra places, it says, the council could be “unable to meet its statutory duty of providing adequate school places”.

Councillor Guy Renner-Thompson, the Cabinet member for children and young people, said the investment would help children with special educational needs “access the support and education they need within their local communities”.

What it means for you

  • For families in Ashington: this adds specialist SEN places at a secondary school in the town itself.
  • When: the work now goes out to procurement. The council expects it to be delivered in the 2026-27 financial year, which ends on 31 March 2027. It has not given an opening date.