National Highways plans three months of work on the A1 between Felton and Alnwick from 7 December. A 40mph limit applies and nine junctions shut at times.
The A1 between Felton and Alnwick will drop to 40mph for three months from Monday 7 December. National Highways plans junction upgrades and new signs and road markings on the stretch. At times during the work, traffic will be banned from joining or leaving the A1 at nine side junctions.
The work is expected to start at 20:00 on 7 December and run for three months, or until it is finished. That takes it into early March 2027. National Highways set out the plans in a notice of its intention to make a temporary traffic order, published on 12 November.
What the order allows
The restrictions can apply 24 hours a day, at times during the work. The order would:
- set a 40mph limit in both directions for 10,620 metres, from just south of the B6345 bridge at Felton to 1,000 metres south of the A1068 bridge at Alnwick South
- set a 10mph limit over 8,570 metres of that stretch
- close the laybys on both sides over the same 10,620 metres
- close the gaps in the central reservation from the B6345 bridge to 300 metres north of the West Cawledge Park junction
- stop vehicles joining or leaving the A1 at nine junctions
The nine junctions, as the notice names them, are:
- Lane Head
- Leamington (Swarland South)
- Newton-on-the-Moor (South)
- Wittle Crossroads (Newton-on-the-Moor North)
- Whittingham Crossroads (Hampeth South)
- Hampeth North
- Hitchcroft (Shilbottle)
- Deanmoor
- West Cawledge Park
The notice says access will be kept at all times to homes and businesses that can only be reached from the A1. The limits do not apply to emergency vehicles. Signs on the road will show where the restrictions are in force.
The order would come into force on 6 December and can last up to 18 months. That is the legal maximum for a temporary order, not the length of the work.
What it means for you
If you live in Swarland, Newton-on-the-Moor, Shilbottle or Hampeth, the junction you use to reach the A1 may be shut at times during the work. The notice does not say which junction closes on which day, or whether closures will be overnight or around the clock.
National Highways publishes a seven-day road closure report that lists carriageway and slip road closures about a week ahead. Closures for this scheme should appear there from early December. We track that report every week on our Northumberland roadworks page.
Anyone driving between Morpeth and Alnwick this winter should allow extra time, and should not plan to stop in a layby on this stretch.
The A1 south of Morpeth is still at 40mph too
The Felton to Alnwick scheme starts while two other A1 jobs are still running south of it. A 40mph limit has applied between the Warreners and Earsdon Moor junctions, north of Morpeth, since 11 September, for 13 weeks. Another has applied between Seaton Burn and Stannington since 23 September, for 11 weeks. Counted from those start dates, they run to around 11 and 9 December.
National Highways’ current closure report books the southbound carriageway from Stannington to Seaton Burn shut overnight, 20:00 to 06:00, on 19, 20, 22, 23 and 24 November.
Sources
- Public Notice Portal: The A1 Trunk Road (Felton to Alnwick) (Temporary Restriction and Prohibition of Traffic), National Highways notice published 12 November 2026
- National Highways: road closure report, workbook for 19 to 25 November 2026, read 19 November